Giyani Metals Corp Announces July 2024 Demo Plant Construction Update

Giyani Metals Corp. (TSXV:EMM, GR:A2DUU8), the developer of the K.Hill Battery-Grade Manganese Project in Botswana, has announced an update on the construction of the Demonstration Plant (Demo Plant).

Demo Plant Construction Progress

Significant construction progress was made in July. The company installed five additional modular process skids (Process Modules), bringing the total to seven out of nine. These new modules include purification circuits, a reagent make-up system, a filtration Process Module, and water treatment and storage.

Instrumentation and Electrical Installation

The installation of the instrumentation, electrical cabling, and piping works for the Crystallizer Unit and internal Crystallizer Process Module has started and is nearing completion. This detailed work will extend to other Process Modules sequentially.

Ventilation and Utility Systems

The ventilation system installation is complete, ensuring a safe operating environment within the plant. Additionally, the main reticulation for the utility steam system has been installed and successfully pressure tested.

Civil Works and Waste Storage System

Civil works for the external waste storage tank system are ongoing. This system will collect process discharge and waste streams for analysis, aiding in the design and cost optimization of the water recovery system for the commercial plant.

Simulation Test Work

Simulation test work is progressing on the Yokogawa Distributed Control System (DCS) software, which will control the Demo Plant. This software allows for continuous process flow, which is crucial for understanding how the Commercial Plant will respond before construction.

Project Timeline

The Project remains on track to begin commissioning and producing battery-grade manganese in Q4 2024 for off-taker testing and qualification.

Leadership Insight

Danny Keating, President and CEO, expressed his excitement about the Demo Plant’s progress. He emphasized the importance of the Plant’s ability to operate continuously at a pre-commercial scale for understanding and optimizing the Commercial Plant.

Summary of Construction Stages

The construction involves several stages:
C1 – Mechanical Completion
C2 – Dry testing, direction testing, loop testing
C3 – Cold/Water Commissioning, software testing
C4 – Hot Commissioning with reagents and steam
C5 – Production Ramp-up

About Giyani Metals Corp.

Giyani Metals Corp. aims to become a leading producer of sustainable, low-carbon, high-purity battery-grade manganese for the electric vehicle industry. The company has secured financing from strategic partners to progress the K.Hill project to construction.

Qualified Persons / NI 43-101 Disclosures

A National Instrument 43-101 (NI 43-101) technical report, including results of the PEA and the MRE, can be found on SEDAR+ and the Company’s website.

Contact Information

Danny Keating, President & CEO
dkeating@giyanimetals.com
Charles FitzRoy, Head of Corporate Development & Strategy
cfitzroy@giyanimetals.com

Disclaimer:
The content presented on this page has not been manually verified by our team. While we strive to ensure accuracy, we cannot guarantee the validity, completeness, or timeliness of the information provided. Always consult with appropriate professionals or sources before making any decisions based on this content.



The image is randomly selected and doesn’t necessarily represent the company or the news below.

Click here for more Company News